NRW secures $137m contract to deliver works on the WA Koodaideri iron ore project

1 min read
Monica Gameng   |   May 17, 2019

NRW Holdings has secured a new $137 million contract from Rio Tinto for the delivery of the Koodaideri Rail Formation South Earthworks as part of the Koodaideri iron ore project in the Pilbara, Western Australia.

Scope of works under this contract include the construction of a 73-kilometre rail embankment as well as a new 44-kilometre mine access road that connects to the Great Northern Highway and associated works along the Koodaideri rail alignment.

Works are expected to commence in August of this year and will take up to 70 weeks to complete. Approximately 300 workers are anticipated to be on site at peak construction.

“I am delighted that NRW has been awarded the Koodaideri Rail Formation South contract by Rio Tinto," NRW Holdings Chief Executive Officer Jules Pemberton said.

This contract win is in addition to NRW’s $65 million contract to deliver bulk earthworks and drainage works for the Koodaideri project that was awarded earlier this year.

Earlier this month, the Acciona-Clough joint venture was also awarded the contract to deliver the northern rail formation.

The Koodaideri iron ore project is located about 110 kilometres from Newman and it is set to become Rio Tinto’s new major Pilbara hub. The development will comprise of a processing plant and infrastructure which includes a 166-kilometre rail line that connects to Rio Tinto’s existing Pilbara rail network, an airport, support facilities and accommodation for mine workers.

The entire Koodaideri development is expected to support up to 2,000 jobs during construction and up to 600 ongoing positions once it is operational.

The Koodaideri mine is set to be operational by 2021, with a capacity of up to 43Mtpa.

Watch this space for the latest industry news and project updates by subscribing to Felix Project News today.

 

Source: Australian Mining; The West Australian; Inside Construction

Monica Gameng
As Felix's Marketing Assistant since 2015, Monica is responsible for researching and sharing new and progressing projects within the construction and mining sectors in Australia. It's no surprise that Monica has her finger on the pulse of Australian major projects given she has produced more than 1,000 posts. She truly is an industry expert.
Follow me:

Related Articles

Projects
Acciona-Clough JV wins civil works contract for Rio Tinto's Koodaideri Project

The joint venture between Acciona and Clough has been awarded the contract to deliver civil works on the northern rail formation at Rio Tinto’s Koodaideri iron ore project in Western Australia’s Pilbara region.

Projects
NRW wins new $95m contract for works at Koodaideri project WA

Rio Tinto has awarded a new $95 million contract to NRW Holdings for mine pre-strip works at the Koodaideri iron ore project in the Pilbara, Western Australia.

Projects
NRW awarded $65m bulk earthworks contract on Rio Tinto Koodaideri project

NRW Holdings is set to deliver bulk earthworks at the Koodaideri iron ore project in Western Australia’s Pilbara region with a $65 million contract win from Rio Tinto.

Get the latest project news

Formerly known as the PlantMiner blog, Felix Project News is Australia's top 10 Construction blog. Join thousands of construction and mining pros getting the best content right in their inbox.
  • updates on Australia's pipeline of state and federal projects
  • fresh contract awards from major contractors and builders

If you're looking to contact us about other matters, please contact us.

Select your preferred email frequency
Which best describes you?
Please Select*
  • Please Select*
  • I hire plant, equipment or subcontractors
  • I supply plant, equipment or subcontracting trades
  • Both
  • Other

By submitting this form you agree with the T&Cs and Privacy Policy and you consent to allow Felix to store and process the personal information submitted above to facilitate your request.