NRW wins new $95m contract for works at Koodaideri project WA

Monica Gameng   |   August 31, 2019

Rio Tinto has awarded a new $95 million contract to NRW Holdings for mine pre-strip works at the Koodaideri iron ore project in the Pilbara, Western Australia.

Under this contract, NRW will undertake the development of mining pre-strip as well as earthworks infrastructure that will enable mining operations to commence.

Scope of works will include mobilisation and site establishment; drill and blast services; construction of access roads, haul roads and drainage; as well as clearing and stripping topsoil and subsoil.

Work is anticipated to begin in November of this year and will take up to 78 weeks to complete. The company will be utilising major plant from its existing fleet.

At peak construction, more than 150 site-based personnel is going to be needed on site to deliver the works.

In May 2019, NRW was awarded a $137 million contract to deliver the Koodaideri Rail Formation South Earthworks. You can read more about it here.

“NRW looks forward to continuing our relationship with Rio Tinto and supporting their iron ore operations in the Pilbara,” NRW Holdings Chief Executive Officer Jules Pemberton said.

The Koodaideri iron ore project is located approximately 110 kilometres from Newman. This mining operations is set to become Rio Tinto’s new major Pilbara hub. The project will comprise of a processing plant and infrastructure, including a 166-kilometre rail line that will link Rio Tinto’s existing rail network, an airport, support facilities and accommodation for mine workers.

The entire Koodaideri development is expected to support up to 2,000 jobs during its construction and about 600 ongoing positions once it is operational.

The Koodaideri iron ore project is set to begin operations by 2021 with a capacity of up to 43Mtpa.

Stay up to date with the latest industry news and project updates by subscribing to Felix Project News today.

 

Source: Australian Mining; Mining Weekly; MiningNews.net

Monica Gameng
As Felix's Marketing Assistant since 2015, Monica is responsible for researching and sharing new and progressing projects within the construction and mining sectors in Australia. It's no surprise that Monica has her finger on the pulse of Australian major projects given she has produced more than 1,000 posts. She truly is an industry expert.
Follow me:

Related Articles

Projects
Rio Tinto invests $98m to build new solar farm for Koodaideri Project

Rio Tinto will be committing to renewable energy to power operations at its Koodaideri mine in the Pilbara with a $98 million investment to build a new solar farm together with a lithium-ion battery storage system.

Projects
NRW secures $137m contract to deliver works on the WA Koodaideri iron ore project

NRW Holdings has secured a new $137 million contract from Rio Tinto for the delivery of the Koodaideri Rail Formation South Earthworks as part of the Koodaideri iron ore project in the Pilbara, Western Australia.

Projects
Barminco wins $95m mining services contract for Mt Colin copper mine in QLD

Round Oak Minerals has appointed Barminco Holdings as the preferred contractor for the Mount Colin underground mine in Queensland, with the awarding of a four-year mining services contract - with a one year option to extend - valued at approximately $95 million.

Get the latest project news

Formerly known as the PlantMiner blog, Felix Project News is Australia's top 10 Construction blog. Join thousands of construction and mining pros getting the best content right in their inbox.
  • updates on Australia's pipeline of state and federal projects
  • fresh contract awards from major contractors and builders

If you're looking to contact us about other matters, please contact us.