PlantMiner’s Online Construction Marketplace is routinely relied upon for the procurement of plant and equipment on some of Australia’s largest projects. We've compiled this list of the top 6 construction projects that have come through our marketplace so far in 2019, to give insight into some of the opportunities that were available to PlantMiner suppliers (and that you may have missed out on) this year alone.
Source: The Australian
The largest renewable project in Australia, Snowy 2.0 is the first major expansion of the Snowy Mountains Hydroelectric Scheme since its initial phase back in 1974. Once constructed, it will create up to 2,400 jobs and generate enough energy to power 500,000 homes. The Federal Government has officially approved the project in February 2019, and committed to an investment of up to AUD 1.38 billion. Access roads are currently being completed on site.
Some of the items sourced through PlantMiner for this project include: articulated dump trucks, water carts, fuel tanker trucks, excavators (over 60T), compactors and dozers.
Source: Geotechnical Engineering
This $11 billion transport infrastructure project will create a 9km twin rail tunnel under the city, vastly improving the efficiency of Melbourne’s central rail system. By removing three of the city's busiest train lines (Pakenham, Cranbourne, and Sunbury) and adding five new underground stations, an additional half a million passengers will be able to travel across the network during peak periods.
Early works on the project were well underway by the start of 2019, with the first tunnel-boring machine arriving in February. The project is currently scheduled for completion in 2025.
Some of the items requested through PlantMiner for this project include: telescopic clamshell excavator, self-propelled modular transporter, HIAB crane, tipper trucks, front-end loaders, and Moxy dump trucks.
Source: International Mining
Owned by the world’s second largest mining corporation, Rio Tinto, the $3.8 billion Koodaideri Mine in Western Australia’s Pilbara region has been undergoing preparatory works since mid-2018. Rio Tinto has called Koodaideri their first ‘intelligent mine’, and have placed orders for autonomous trucks and drills, with plans to make it their most technologically-advanced mine to date.
Phase 1 of construction will start this year, with initial production kicking off in 2021. Once completed, the iron ore mine will have an annual capacity of 43 million tonne.
Over 40 Requests for Quotation have been submitted via PlantMiner’s Marketplace for the Koodaideri Mine in 2019 alone. Some of the items requested include: scrapers, dozers (D8-D10), graders, excavators (20-50T), articulated dump trucks (40T+), smooth drum & padfoot rollers (16T+), telehandlers, forklifts, semi water carts, and site vehicles (dual cabs, buses).
source: Tilt Renewables
Located approximately 23km north-east of Mortlake, the $560 million, 80-turbine renewable project got started in January of this year. The expected output of 336 megawatts will mean that the wind farm will be able to produce enough electricity to power roughly 245,000 homes. Construction is expected to be fully completed in late 2020.
Some of the items requested through PlantMiner for this project include: rough terrain cranes, padfoot rollers, front-end loaders, water carts, trenchers & trench rollers.
source: NSW Government
The $16 billion, 33-kilometre motorway is a part of an overarching transport plan to ease gridlock traffic and better connect Western Sydney to the airport and Port Botany Precinct. The project will greatly reduce traffic congestion in the nation’s largest city, a problem costing roughly $6 billion annually. The improved efficiency of motorists by the masses will also reduce greenhouse gas emissions by over 610,000 tonne a year!
The nation’s largest road project is now over half-way completed, with full completion estimated for 2023.
17 Requests for Quotation have been submitted through the PlantMiner Marketplace for WestConnex. The majority of requests were for civil plant, including; excavators, graders, rollers, trucks & dogs, tippers, pumps, and dozers.
Source: North Queensland Register
With mining leases approved and construction underway, the $21.7 billion mine, rail and port project in Queensland’s Galilee Basin is set to become Australia’s largest ever coal mine. In its first stage, the mega mine will produce 10 million tonnes of coal per annum, creating roughly 5,000 jobs during construction and another 4,500 during the peak of its operations.
Some of the items requested through PlantMiner for this project have included: compactors, rollers, scrapers, graders, dozers, excavators, and fuel trucks.
Other than being worth hundreds of millions of dollars, what do all these projects have in common?
They were all listed on PlantMiner, Australia’s Largest Online Construction Marketplace.
Thousands of people from all facets of the industry take advantage of our platform’s procurement tool to connect with local contractors more efficiently - and our suppliers win millions of dollars’ worth of work each and every month off the back of these requests.
If you’ve been looking for a way to get your foot in the door on these blockbuster jobs, or if you just want to pick up some extra work in your area, PlantMiner may be able to assist.
Take a hands-on approach, and find out about our award-winning service and how you can list your plant and/or equipment or subcontracting business by clicking HERE.
Source: Adani Australia (1); Australian Mining (2); Australian Mining; Delivering for all Victorians; Infrastructure New South Wales; ItNews; Metro tunnel; news.com.au; New Internationalist; Queensland Government; SMEC; Tilt Renewables; Victoria's Big Build; WestConnex
Major construction activities have now commenced on the Toowoomba Second Range Crossing (TSRC) project. The works follow preliminary construction which commenced in February 2016.
Queensland's residential market is booming - many business are seeing great ROI from capitalising on these projects. But like any construction trend, what's most popular is constantly evolving.
The Brisbane City Council is calling for expressions of interest to design and construct the upgrade of the Inner City Bypass, with the successful tenderer to be announced later this year.
The project was announced in last year's council budget and should be completed in 2018.
If you're looking to contact us about other matters, please contact us.