Santos has completed the commissioning and start-up of the Scotia CF1 project in Queensland. The company has stated that the project was completed ahead of schedule and under budget.
According to Santos Managing Director and Chief Executive Officer Kevin Gallagher, the delivery of the project was outstanding, completed well ahead of schedule and well under budget.
“The project was estimated to cost $493 million, but the team has delivered it for $416 million, 16 per cent under budget.
“Site infrastructure is also running three months ahead of schedule and some of the well completions are a year ahead of time,” Mr Gallagher said.
Source: Santos
The Scotia CF1 project involved the expansion of the compression plant and field from 23 to more than 100 wells. The project also included building 85 kilometres of linear infrastructure as well as two 4G communications towers and an irrigation system for water treatment. Construction of the Scotia expansion employed more than 400 people.
Scotia CF1 - located in the Bowen Basin, 340 kilometres northwest of Brisbane - will be supplying approximately 70 terrajoules (TJ) a day at peak production in 2019 which will significantly boost gas supply to the Santos GLNG project as well as benefitting both the east coast domestic gas and export LNG markets.
Receive the latest industry news and project updates straight to your inbox by subscribing to Felix Project News today.
Source: Australian Mining, Santos
A new milestone has been reached on the $50 million upgrade to Ballarat Station in Victoria with the release of early designs for community feedback.
Update on Brisbane Airport projects including phase two of the $1.4 billion Parallel Runway project and the recently completed $35 million Overlay Project.
The $2.6 billion Sydney Gateway development in New South Wales is progressing well towards completion and providing a new toll-free connection from St Peters Interchange.
If you're looking to contact us about other matters, please contact us.