Several changes have been made to the final section of South Australia’s North-South Corridor after the State Government undertook a comprehensive design and financial review on the River Torrens to Darlington (T2D) project.
The approximately $15.4 billion project will now include the removal of large, elevated roadways as well as adding new entry and exit ramps.
The 10.5-kilometre T2D section of the North-South Corridor will consist of two sets of twin tunnels, lowered and ground-level motorways along with overpasses and underpasses at key intersections.
Key changes proposed for the project include:
A revised delivery program was also recommended following the project review, which will get construction of the Southern and Northern Tunnels delivered sequentially rather than overlapping. This delivery program is a more realistic approach to project timing and market capacity.
Some properties earmarked for acquisition before the review and revision of plans will no longer be required, but the updated designs will result in a net increase of 112 properties required to build the T2D project.
Early works are already underway and main construction will begin in 2025, with the tunnel boring machine in the ground working on the Southern Tunnel in 2026.
A series of community information sessions is going to be held in early 2023 along the project alignment where the project team will engage with interested stakeholders to gain local insights that will further inform the project's design.
The procurement process for T2D is also anticipated to commence in early 2023, with the contract to deliver the project awarded in 2024.
The River Torrens to Darlington Project is due to be completed in 2031 and it will complete the 78-kilometre non-stop motorway between Gawler and Old Noarlunga as well as allow motorists to avoid 21 sets of traffic lights between the River Torrens and Darlington.
Source: SA Department of Infrastructure and Transport – Torren to Darlington (1, 2); ABC News; Infrastructure Magazine
The Australian Government has committed $63.5 million towards the Dunheved Road upgrade in New South Wales’ Penrith region, taking the total federal funding for this project to $127 million – which is the full projected value of the upgrade.
The final designs for the new road bridge that will replace the dangerous and congested level crossing at Station Street in Beaconsfield, Victoria have been released.
A major milestone has been reached on South Australia’s $14 million Lobethal Freight Access Upgrade with the design and build contract awarded to McConnell Dowell Construction.
If you're looking to contact us about other matters, please contact us.