Felix Project News | Australia's Favourite Construction Blog

Major tunnelling works to start on Sydney's $3b NorthConnex project

Written by Sophia Rostron | Mar 29, 2016 2:00:00 PM

The Australian and NSW governments have announced that major tunnelling works on Sydney's NorthConnex project are due to begin in April, with final preparatory works now well advanced. 

NorthConnex project: A quick guide to the $3b mega-project

Estimated project cost: $2,987,000,000.

Proposal: In early 2012, the NSW Government received an unsolicited proposal from the project's private sector sponsors; Transurban and the Westlink M7Shareholders, to manage the design, construction, maintenance and operation of NorthConnex. In early January 2015, the Australian and NSW governments gave planning approval, and reached contractual and financial close in late January 2015. 

Funding: The $3 billion project, consisting of a construction budget of $2.65 billion in addition to land and project delivery costs, is funded through toll charges with a contribution from the NSW and Federal Governments of up to $412.33 million each, including the use of Hornsby Quarry for spoil management.

Design & Construct Contract: The Project Sponsors are managing the design and construct contract procurement process(the tender process) with the involvement of the NSW Government. Tender bid submissions period closed at the end of November 2013. In March 2014, the Government announced the Lend Lease Bouygues joint venture as the preferred tenderer and project scheme. UGL Limited announced in September 2015 that it has entered into a four year Alliance Agreement with the Lend Lease Bouygues Joint Venture (LLBJV) on the NorthConnex Project. 

Overview: The completed$3 billion NorthConnex project will better link Western Sydney and the Central Coast, creating twin nine-kilometre tunnels under Pennant Hills Road, which is regarded as one of the most congested roads in the country.  The tunnel motorway includes interchanges to the north and south to accommodate connections at either end of the project. When complete in 2019, it will allow traffic to bypass up to 21 sets of traffic lights, link Sydney's north to the Orbital network, and enable travel from Newcastle (M1) to Melbourne without a single set of traffic lights.

Major tunneling works: The two main tunnels are each around nine kilometres long. Additional tunnels will be excavated for on and off-ramps at both the northern and southern interchanges. The deepest part of the NorthConnex tunnel would be around 90 metres in order to pass under the NorthWest Rail Link tunnel at Beecroft. Over half the tunnel is more than 60 metres deep – about the height of the Sydney Opera House.

Image: NorthConnex Tunnel 

The main tunnels would generally be excavated to be around 14 metres wide, with a height of about eight metres. The tunnel excavation would be carried out using road headers and surface miners. Material would be removed from the tunnel at the nearest construction compound where it would be stockpiled and removed by haulage trucks. Member for Berowra Philip Ruddock said "the southern interchange will be used as a temporary construction compound until project completion with almost 615,000 cubic metres of spoil from tunnelling expected to be removed from the two 30 metre deep tunnel shafts.” Finishing work including tunnel lining, pavement construction and mechanical and electrical fit-out would be undertaken progressively following tunnel excavation.

Image: NorthConnex Proposed Construction Program

Want to received project news and updates straight to your inbox? SUBSCRIBE TO FELIX PROJECT NEWS!