It's a very exciting time to be involved in the Darling Down's construction industry with the $1.6 billion Toowoomba Second Range Crossing Project (TSCR) commencing construction in late April 2016. In fact, the project itself is generating so much interest that visitor centres and information booths are being set up around the region. Learn more about the Nexus's April TSRC update below.
Activities will occur concurrently across all areas, promising a hotspot of plant and equipment. To name a few, expect to see excavators, rollers, compactors, truck cranes, franna cranes, forklifts, air compressors, compactors, portable toilets, generators and more.
The project, which Nexus says will be build mostly by local workers, will take about three years to complete. The focus of construction for the $1.6 billion project, which will transform the region's road network, will be on vegetation clearing and works on structures and earthworks. If you haven't already, check out the full TSRC procurement schedule.
The initial construction activites to commence in late April will include:
Early works including geotechnical investigations, surveying, flora and fauna assessments and site establishment works are all progressing well in the lead up to construction. The site compound at Hermitage Road, Cranley is almost complete with carpark construction and landscaping underway.
EOIs for work packages are still underway but we should start to see contract awards start to trickle in soon. Watch this space!
More than 1500 suppliers, subcontractors and job seekers attended a series of procurement and employment information sessions for the Toowoomba Second Range Crossing project late last year. According to a Transport and Main Roads spokeswoman, interest has only increased. The soon-to-be set up booths will provide the community with up-to-date project information, including fact sheets, construction notifications and other resources.
If you're interested in attending drop-in information sessions to find out more about the project, check out the dates and locations here.
Otherwise, subscribe to Felix Project News and get TSRC updates straight to your inbox -procurement dates, contract awards, construction timelines and more.
More than ten years of construction, 16 projects already completed or in progress, and $8.5 billion in federal and state funding for material and works - the Bruce Highway upgrade programme is a massive project. It requires a workforce of thousands and hundreds of companies to build all the different projects. In a release titled "Coalition delivering on plan to 'Fix the Bruce Highway", Federal Minister for Infrastructure and Transport Darren Chester has identified the next eight projects the Coalition Government is working to deliver.
As part of the $1.3 billion CityLink Tulla Widening project, upgrades have begun on the CityLink between Bulla Road and Bell Street. The wideing will involve upgrades to 24 kilometres of CityLink and the Tullamarine Freeway. Once the project is completed, congestion will be reduced and provide a more efficient and smoother journey.
Straight from Nexus Infrastructure, we deliver the latest construction update from the TSRC project.
If you're looking to contact us about other matters, please contact us.