The Etheridge Shire Council has green-lighted the development of the Kidston 2 solar farm (K2-Solar), which will be located approximately 270 kilometres north west of Townsville in North Queensland.
This project by Genex Power will involve the construction of a 270MW solar farm that is going to be co-located with the 250MW Kidston 2 pumped storage hydro project (K2-Hydro).
Source: Genex Power
In December 2017, UGL Limited – a CIMIG Group member – was selected as the preferred engineering, procurement and construction (EPC) contractor for K2-Solar.
Genex Power is currently advancing towards closing the EPC contracts with UGL for K2-Solar as well as with the McConnell Dowell – Downer EDI joint venture for K2-Hydro. The two EPC contracts are expected to be finalised by the end of June 2018. The company is also focusing on bringing in financial close for the entire Kidston 2 Hydro-Solar project.
“After several months of detailed market engagement, we are now in negotiations in regards to securing debt funding for our Kidston Stage 2 project with a select group of partners. Genex’s main focus remains on progressing the Kidston Stage 2 projects to financial close in calendar year 2018,” Genex Power Managing Director Michael Addison said.
Stay up to date with the latest industry news and project updates by subscribing to Felix Project News today.
Source: PV Magazine, Renewables Now
A new large-scale battery storage system near Armidale is a step closer to supplying clean energy to 60,000 homes after the New South Wales Government gives the green light to its development.
The first sod has been turned to signal the beginning of construction of the $1.62 billion Beveridge Intermodal Precinct in Melbourne’s north.
The Games Independent Infrastructure and Coordination Authority (GIICA) has appointed a Delivery Partner to deliver 17 new and upgraded 2032 Olympic and Paralympic Games venues across Queensland.